More progress on dome at Site #1

# Domes

schedule 2017-06-27
Matthew Lehner

Today we got the shutter tracks sealed with putty, got the upper shutter installed with the motor and drive, and got the electrical installation completed. The replacement  bottom shutter got flagged for further inspection when going across the border this morning, so they only got as far as Ensenada today. They will now deliver the shutter tomorrow afternoon. After delivery, we will have the dome completed within a couple hours.

Here are a couple photos from today:

First top shutter section being lifted into place.


Middle top shutter section being lifted into place.


Top shutter completed.