Dome at Site #3 completed

# Enclosures

schedule 2017-07-15
Matthew Lehner

We completed the assembly of the dome at Site #3 early this morning, and the paint crew went to work on it immediately. They finished priming the dome today, and will hopefully get it painted tomorrow. The crane is scheduled to arrive at SPM Monday morning, and we plan to have all three domes installed by the end of the day Monday.

Using the forklift to move one of the top shutter sections from the staging area near the control room to Site #3.


Installation of the lower shutter.


Completed dome after priming.