We completed the crane work at Site #1 early this afternoon. This was the last site to be done, so we are now done with all of the lifting.
We plan to spend the afternoon moving two of our primary mirrors out of the 2m building so they can begin coating the other mirror. We expect all mirrors to be coated by the end of next week.
Ruben and his crew are back and they have been working to wrap up the enclosure construction. The main things they need to finish are the installations of the observing chamber doors and the exhaust fans. They finished work at Site #2 yesterday, and are working on Site #3 today.
Here are some photos from today.
Focus housing after lifting to the observing floor at Site #1.
Getting the center section and primary mirror cell to the enclosure entrance for separation.
Lifting the center section.
Center section after installation.
A bag full of boxes of various parts that we will need in the short term.
Everything else for the Site #1 telescope now loaded onto the flatbed and delivered to the site. This is the last set of items to be lifted.
Dec drive mechanism on its way up.
Everything now successfully lifted to observing floor.
Exhaust fans installed in Site #2 enclosure.
Installation of door to observing floor at Site #2 finished.