TAGS
Introduction (2)
Enclosures (12)
Domes (16)
Telescopes (27)
Camera (1)

Blog


After finishing the crane work, we spent the past few days mostly finishing up some unexciting, random tasks that needed to be done. We filled in the holes in the observing floors created by trimming the corners off of the lift tables, finished most of the stuff I wanted to do during the last trip (dome home switches, mounting dome control electronics), relocated the lift table hydraulics controls from the trap door in the observing floor to the wall, cleaned all of the trash that the construction crews left on the ground floor of each enclosure, and gave all of the enclosures a thorough vacuu...
2017-09-14 #Telescopes

We completed the crane work at Site #1 early this afternoon. This was the last site to be done, so we are now done with all of the lifting.We plan to spend the afternoon moving two of our primary mirrors out of the 2m building so they can begin coating the other mirror. We expect all mirrors to be coated by the end of next week.Ruben and his crew are back and they have been working to wrap up the enclosure construction. The main things they need to finish are the installations of the observing chamber doors and the exhaust fans. They finished work at Site #2 yesterday, and are working on Site...
2017-09-07 #Telescopes

We installed the pedestal and fork at Site #1 this morning. We got the primary mirror cell/center section/focus housing stack loaded onto the flatbed and up to the site for installation this afternoon, but a thunderstorm came through so we covered everything with a tarp and called it a day. We will get back to work tomorrow morning.Here are a few photos of today's activities. Getting the pedestal out of the container. Getting the fork out of the container. Lifting pedestal. Lifting the fork. Pedestal and fork installed.
2017-09-07 #Telescopes

Today we finished all of the crane work at Site #3. We started this morning with the fork and the primary mirror cell/center section/focus housing bundle, and after lunch we lifted everything else: counterweights, Dec drive, electronics rack, trusses, and lots of boxes using a nifty cargo bag that Liliana provided. We will start on Site #1 tomorrow morning.Here are some photos. Not too many today, since most of them look like those from the work at Site #2. Lifting fork out of container and onto flatbed. Getting primary mirror cell/center section/focus housing stack out of container. At Site...
2017-09-06 #Telescopes

Yesterday it was misting most of the day so we did not do any crane work. Instead we continued the work on the lift table modifications. Today, however, was very sunny, so we were able to finish the crane work at Site #2.  We also had time to install the pedestal at Site #3, and weather permitting, we expect to finish most, if not all, of the crane work at that site tomorrow.We started the day by lifting the spyder ring and focus housing, after which we separated the center section from the primary mirror cell and lifted and installed it. (The mirror cell stays on the ground floor until t...
2017-09-05 #Telescopes

We installed the first pieces of the telescope at Site #2 today. The pedestal and fork are now in place, along with the HA and fork counterweights. The crane had another fuel line issue this morning after the installation of the pedestal, so we went and unloaded the rest of the parts from the container while the mechanic fixed the problem. While finishing the installation of the fork, the weather turned bad so we closed up the dome and headed back to the dormitory until things cleared up. We were able to install some counterweights on the fork this afternoon, as well as get the HA drive mecha...
2017-09-02 #Telescopes

We finished preparations for the telescope installation yesterday. All the pier holes are finished, and the domes, lift tables, and hoists are all operational. The cranes also arrived yesterday. (We are using two cranes: a large crane to do the lifting and a smaller crane with a flatbed to pull the parts from the containers and transload them to the sites.) The small crane arrived at the observatory last night, while the large crane made it as far as the park entrance since it needed to be delivered on a large flatbed trailer. This morning we began the work of transloading the telescope pedest...
2017-09-01 #Telescopes

I got back to SPM yesterday with Ian Huss and Justus Drake from DFM Engineering to start work on the telescope installation. The crane will arrive in time to begin the heavy lifting Thursday morning, but we wanted to spend a couple days preparing. In short, we need to get all of the nuts, bolts, and various pieces of equipment required for the heavy lifting organized and put into place. In addition, we wanted to get the big parts in the containers ready for the lift, so we need to unbolt everything from the containers, and get the rigging set up as much as possible. Finally, we need to prepare...
2017-08-30 #Telescopes

My trip to Mexico is over. We wrapped up a few things before I left. In no particular order:Electrical power:The transformer at Site #2 that brings power to Site #3 died, so no electricity at Site #3. Electrical crew should be replacing it this week, as well as installing a new and improved ground system at tall of the sites.Dome azimuth home switches:We got it installed correctly at Site #2. This was after we broke one of the switches because there was a low-hanging bolt on the hydraulics that I missed, it snapped off the top of the switch as it moved by while rotating the dome. We replaced t...
2017-08-20 #Telescopes

The painters finished painting the first dome today at Site #1. They were working on the dome at Site #2 as well, but I didn't make it there this afternoon to check out the progress. I am heading back to civilization tomorrow morning, back to SPM Monday afternoon to finish up dome #3.Here is the dome at Site #1 after painting.
2017-07-06 #Telescopes

The telescopes arrived a little past 9am local time. All three containers were safely offloaded, and nothing appears to be damaged.We began to unload some items in the afternoon. The primary mirrors for telescopes #1 and #3 are now stored at the 2m building near the coating chamber. Tomorrow we will unload the remaining mirrors and start moving the smaller boxed items closer to the telescope enclosures. There are also several parts that will be installed with the domes (azimuthal encoder and home switch, a hoist that hangs from the shutter frame, etc.).Photos below.First truck arriving at obse...
2017-07-04 #Telescopes

The three telescopes have finally cleared customs this afternoon. They will leave Tijuana early Monday morning and arrive at SPM late afternoon or early evening.
2017-07-01 #Telescopes